Marikana Community Centre Construction
22 Sep 2026 FY 2025/2026
58%
Overall Progress
R12.5M
Total Budget
R7.3M spent (58%)
3,200
Beneficiaries
3/5
Milestones Complete
Project Details
Status Active
Priority High
Category Infrastructure
Manager Zanele Khumalo
Start Date 01 Jun 2024
End Date 31 Dec 2025
Location Marikana Township
Construction of a modern community centre
Milestones
Foundation & Groundwork
Site clearing and foundation work
Completed
Due: 30 Sep 2024
Structural Frame
Steel and concrete frame
Completed
Due: 31 Dec 2024
Roofing & Cladding
Roof and external cladding
Completed
Due: 31 Mar 2025
Interior Finishing
Internal walls, floors, fittings
In progress
Due: 31 Aug 2025
Handover & Commissioning
Final inspection and handover
Pending
Due: 31 Dec 2025